Proposed Schedule for 2026 Road Projects
The following is the proposed schedule for the various roads that are budgeted to be milled and overlaid. Due to fluctuation in asphalt pricing and budgetary constraints, the paving of some roads may be deferred to a later date. Should any changes to this schedule be required, we will send out a notice in advance.
The hours of operation will be approximately 7:00 a.m. to 5:00 p.m. and may change, as necessary.
The project is scheduled to begin in early-July and be completed by early-August.
List of Roads to be Milled and Overlaid
-
Amber Place
-
Bartlett Drive
-
Brittany Place
-
Cathedral Drive
-
Colwyn Terrace
-
Corporate Drive
-
Damson Lane
-
Duchess Place
-
Elberta Drive
-
Henning Drive
-
Horseshoe Lane
-
Jonathan Drive
-
Kelsey Drive
-
Lindsey Place
-
Macintosh Lane
-
North Wales Road (Rt. 309 to Montgomery Glen Drive)
-
Orchard Drive
-
Ravenwood Place
-
Red Haven Drive
-
Stayman Drive
-
Windsor Circle
Additional Information & Safety
During the project, your street will be closed except for local traffic and emergency vehicles. During the milling and paving of your street we are requiring all cars be parked in their driveways. This will assist us in completing this project in a timely manner.
Due to extreme temperatures of the material, it is recommended that you keep children and pets away from the street area where the paving process is taking place. Please avoid driving your vehicle on this material during the placement of blacktop or crack sealer material to avoid damage to your vehicle. We will not be held liable for any resulting damage.
Each property owner should check their mailbox front to ensure that it is a minimum of 7 inches behind the face of the curb, which is within federal postal regulations. Prior to the start of the paving project, the homeowner should reset any mailboxes protruding past the minimum measurement of 7 inches behind the face of the curb. This will ensure that the mailbox will not be damaged during the milling and paving operation. Any damage that may occur will be the responsibility of the homeowner.
Please trim any trees or shrubs extending past the edge of the roadway or curb. This will allow our paving equipment to pass safely in front of your property. Montgomery Township will not be responsible for anything damaged in the right-of-way, such as invisible dog fencing, basketball backstops etc.
Visit PennDOT's District 6 Traffic Bulletin for more details.
Visit Montgomery County's Roads & Bridges webpage to learn more about maintenance and improvement.
Sign up to our News and Notices
Stay up to date on the Township's activities, events, programs and operations by subscribing to our News and Notices.