Penn Medicine Project

Overview

Penn Medicine is constructing a four-story outpatient medical center and adjacent parking garage on an 11.9-acre site along DeKalb Pike between Welsh Road and Gwynmont Drive. Approved by the Township in 2023, the facility will offer primary care, specialty care, labs, physical therapy, orthopedics, and other outpatient services, with no overnight or 24-hour operations. Site improvements include new landscaping, stormwater management, sidewalks, lighting, and a new traffic signal. Construction began in 2025 and is progressing on schedule, with work now focused on building interiors, parking garage construction, and site infrastructure. The project is expected to reach substantial completion in spring 2027.

The Township will continue to post updates to this page when new information becomes available.

Project Details

The Trustees of the University of Pennsylvania, Owner & Operator of the University of Pennsylvania Health System, submitted a land development application to construct an ambulatory health care center on an 11.9-acre parcel on the east side of Dekalb Pike, between Welsh Road and Gwynmont Drive, in the C Commercial zoning district, permitted by conditional use.

The Board of Supervisors granted conditional use on April 10, 2023, and conditionally approved the land development application on August 28, 2023. The plan includes a 4-story ambulatory health care center and an adjoining 4-level above-ground parking garage with an additional underground parking level.

The facility will provide outpatient medical services, including labs, physical therapy, primary care, and orthopedics, without overnight or 24-hour operations. The site will be improved with landscaping, stormwater management, lighting, an internal walking path, pedestrian crosswalks, and a traffic signal at Dekalb Pike and Gateway Center Drive/Penn Medicine Drive.

View the Penn Medicine Conceptual Plan

View the Penn Medicine Presentation to the Board of Supervisors on September 18, 2024.

View the Penn Medicine 2023 Conditional Use Presentation.

Penn Medicine Proposed East-West Cross-Section

 

Blasting is scheduled March 18 through April 11, 2025

All blasting activities are regulated by the PA Department of Environmental Protection (DEP). Please call DEP at 484-250-5900 with any questions or concerns.

View the Blasting Scope of Work Drawing.

Design and permitting: July 2024 – February 2025
Construction: March 2025 – March 2027
Substantial completion: Spring 2027

Fall is the optimal season for landscape buffer installation. Final timing is pending confirmation from Penn Medicine.

The site will include:

  • A 50-foot wide screen buffer along the north and east property boundaries.
  • A 20-foot softening buffer along the southwest and southeast boundaries.
  • An 8-foot tall wood board privacy fence located within 5 feet of the property line.
  • 100% visual screening within 4 years for screen buffers.
  • 50% visual screening within 5 years for softening buffers.

Source: Land Development/Landscape Plan

Sections of the sidewalk along Dekalb Pike will be closed during construction. Please follow the pedestrian crossing signs to navigate the area safely.

View the Penn Medicine Pedestrian Detour drawing.

The plan includes:

  • Removal of 237 trees between 8"–23" diameter and 12 trees between 24"–48" diameter.
  • Specific removal of a grouping of Black Locust trees along Trotter Lane.

To meet township requirements, the project will plant:

  • 129 new trees, including:
  • 67 shade trees
  • 72 flowering trees
  • 26 evergreen trees

Source: Land Development/Landscape Plan

Visual cross sections from the landscaping presentation show:

  • East-West and North-South views from residential areas. 
  • Placement of fencing, berms, and landscaping relative to the building.

These visuals do not specify whether the landscaping shown reflects installation or full maturity.

Source: Conditional Use Presentation

Project Updates

Update Date: July 23, 2026

MOB

  • Level 1, 3, and 4 overhead mechanical, electrical, plumbing, and fire protection piping and ductwork.
  • Level 1 and 2 inwall rough ins and piping.
  • Level 2 drywall hanging, taping, and finish (TAKT Zone 1,2, and 3).
  • Level 3 interior wall framing.
  • Level 4 priority wall framing, exam rooms, toilet pods, and infusion bay pod deliveries and install.
  • Continuation of service elevators installation.
  • Innovation glass curtain wall installation.
  • Finishing LINAC lead block walls and utility penetrations shielding.
  • High roof insulation and membrane finalization (pending load zone areas).
  • Dock levelers installation finalization.
  • Sealing joints and caulking around the building exterior.
  • Passenger elevator pit prep work.

Parking Garage

  • Caulking and joint sealing prep work.
  • PG walls pressure washing.
  • Slab on grade concrete slab prep and pour.
  • Underground electrical and drainage pipes layout and installation.
  • Geothermal vault work - finalization of pending works and repairs.

Site

  • Excavating front trenching around the site gate.
  • Stormwater mains and manholes layout and install.
  • Site lighting excavation and conduit install.

Update Date: July 23, 2026

MOB

  • Level 1, 3, and 4 overhead mechanical, electrical, plumbing, and fire protection piping and ducts
  • Level 2 fit out - Framing - inwall electrical and plumbing, and drywall
  • Install of prefabricated bathrooms and exam rooms on Level 1, 3, and 4
  • Service Elevators installation
  • Innovation glass curtain wall installation
  • Laying of LINAC lead blocks
  • Painting masonry at the back-of-house and drywall at innovation soffit wall
  • Roof insulation and membrane
  • Dock levelers installation
  • Sealing joints and caulking around the building

Parking Garage

  • Precast welding and detailing
  • Concrete prep and pour
  • Damp proofing and backfilling lower-level grade walls
  • Electrical and drainage piping core drilling and installation
  • Geothermal vault work completion

Site

  • Retaining wall install
  • Grading work around gate B
  • Sanitary and stormwater mains layout and install
  • Site lighting layout, excavation, and install

Update Date: June 22, 2026

MOB

  • Overhead Mechanical, Electrical, Plumbing, and Fire protection (MEP/FP) on level 1, 3, and 4
  • Delivery and Install of prefabricated bathrooms on level 1 and 3
  • Interior framing on level 2
  • Electrical and plumbing inwall rough in on level 2
  • Drywall one side on level 2**
  • Priority walls on level 4
  • Freight elevator delivery and installation
  • Linac vault blocks delivery and installation
  • Sunken garden canopy installation
  • Innovation glass curtain wall installation

Parking Garage

  • Precast erection sequence 6 and 7
  • Garage concrete prep and pour across floors
  • Geothermal vault work finalization

Site

  • Water line perimeter link connection
  • Site lighting - electrical work
  • Water line testing
  • Loading dock curb
  • Excavation for front trenching

Update Date: May 22, 2026

MOB

  • Level 1, 2, and 3 overhead - ductwork, sheet metal, electrical, fire protection, and insulation
  • Framing and topping off priority walls on level 1, 3, and 4
  • Stair B handrails install, concrete pour and steel detailing of staircase
  • Setting prefabricated rooms on level 1,  2, and 3
  • Roof Air Handling Units (AHUs) setting and connection
  • Spray fireproofing inspection deficiencies remediation on all floors
  • High roof PVC layer install from plan West to plan East
  • Innovation glass delivery and install
  • Healing garden canopy install and detailing
  • Electrical equipment setting and connection in level 1 electrical rooms
  • Painting TDR uppers and electrical rooms

Parking Garage

  • Precast concrete erection - Sequence 2 and 3
  • Calking and grouting of erected precast pieces

Site

  • Loading dock slab prep, conduits, and concrete pour
  • Site leveling and prep for curbs

Update Date: April 30, 2026

MOB

  • Slab on Grade prep and concrete pour area B section
  • Level 2 overhead - plumbing, sheet metal, fire protection, electrical, and insulation
  • Mechanical, plumbing, and electrical risers on level 4
  • Setting prefabricated pods on level 1 and 2
  • Drywall layout, framing, and topping off
  • Finishing up CMU block wall
  • Spray fireproofing on level 1
  • Roof PVC install
  • Main Entrance canopy detailing and lighting install
  • Air Handling Units (AHUs) delivery and install
  • Electrical equipment delivery and install

Parking Garage

  • Precast crane erection
  • Garage precast concrete components erection

Site

  • Site lighting conduits install
  • Site leveling around MOB
  • Loading dock slab prep
  • Grading for temporary equipment access

Update Date: March 26, 2026

MOB

  • Slab on Grade prep and concrete pour
  • Unitized curtain wall install continuing from sequence 4
  • Exterior thin brick panels erection continuing from sequence 5
  • Roof air-vapor barrier (AVB) install (roof level)
  • Interior priority walls framing level 2
  • Overhead mechanical ducts and piping level 2
  • Overhead plumbing piping level 2
  • Overhead electrical conduits and cable trays level 2
  • Spray fireproofing Level 1 

Parking Garage

  • Grading garage for precast erection
  • Garage precast concrete erection

Site

  • Storm piping install
  • Grading for temporary site access and construction equipment (cranes)

Update Dates: February 6 and February 23, 2026

February 23, 2026

MOB

  • Install of hot and chilled water pipes - risers and mains
  • Main riser ductwork in shafts
  • Layout and install of overhead MEP ducts, piping, and conduit - Level 2
  • Install of air vapor barrier (AVB) on roof
  • Framing priority walls on level 2
  • Fireproofing on level 3
  • Delivery and Install of stair A 
  • LINAC underground electrical conduits
  • Curtain wall install - sequence 1 and 2
  • Panelized exterior thin brick facade install 

Parking Garage

  • Excavation and install of geothermal horizontal manifold piping and vault
  • Backfilling and grading garage in preparation for precast erection

February 6, 2026

MOB

  • Start of Thin brick panels erection
  • Spray fireproofing
  • Hangers and pipes install - mechanical and plumbing
  • Roof insulation - vapor barrier/waterproofing installation
  • HVAC riser duct install in the shafts
  • Sanitary and storm risers
  • Start curtain wall installation
  • Level 2 concrete pour and slab-on-grade concrete pours
  • LINAC underground conduits and underground electrical duct banks 

Parking Garage

  • Geothermal piping and vault install

Site

  • Basin and underground drainage/sanitary

Update Date: January 9, 2026

MOB

  • Slab on Deck concrete pours – North half of building
  • Underground electrical installation
  • Fireproofing
  • Mechanical, electrical, and plumbing overhead rough-ins
  • Exterior wall panel installation

Parking Garage

  • Completion of geothermal well drilling, continue with manifold piping installation

Site

  • Completion of underground basin installation

November 26, 2025

MOB

  • Completion of structural steel detailing and decking
  • Slab on Deck concrete pours – Level 4 south and Roof
  • Concrete pads for mechanical/electrical equipment
  • Underground utility install (electrical, storm water, sanitary piping)
  • Fireproofing

Parking Garage

  • Drilling geothermal wells and manifold piping installation

Site

  • Perimeter fencing and tree installation
  • Underground basin installation

October 31, 2025

Penn Medicine's scheduled November construction activities:

  • Geothermal wells drilling at the parking garage
  • Geothermal manifold and vault excavation and install
  • Underground storm water piping and backfill
  • Foundation walls, rebar, and concrete - healing garden  
  • Underground plumbing and runout piping
  • Steel erection (last sequences 15 & 16), detailing, and deck placement 
  • Backfilling along shared wall areas
  • MEP bang-its and sleeves
  • Storm run piping and basin
  • East side site fencing
  • Steel Topping Off ceremony Nov 6

September 28, 2025

Penn Medicine's scheduled October construction activities:

  • Structural Steel Erection
  • Geothermal Well Drilling
  • Underground Utility Work

September 11, 2025

Fencing and some plantings are scheduled to be installed at the end of the month.

July 16, 2025

Construction crews will begin to work on Saturdays. Work will begin after 8 a.m.

June 24, 2025

The Montgomery Township Board of Supervisors visited the construction site of Penn Medicine.

April 29, 2025

Montgomery Township’s Highway Safety Unit has requested that PennDOT conduct a traffic and speed study of DeKalb Pike to assess current conditions and identify potential safety improvements.

In addition, Penn Medicine is working closely with their contractor to expedite the installation of planned traffic signal upgrades in the area.

We will share the updated project timeline as soon as it becomes available.

April 16, 2025

Drilling for the geothermal well system has begun, and crews will be on-site daily to meet permit requirements and complete inspections.

In addition, installation of the water line loop around the property is now underway. North Wales Water Authority and a third-party firm, Pennoni, are both on-site each day to ensure the work is done properly and safely. Pennoni is also performing compaction testing during backfilling.

This phase of the project will continue over the next several weeks.

Contact Us

Jesse Hill

Director of Planning & Zoning

Address: 1001 Stump Road, Montgomeryville, PA 18936

Phone: 215-393-6920

Email Us

Staff Directory

Hours:

Monday–Friday

8:30 a.m.–4:30 p.m.

Sign up to our News and Notices

Stay up to date on the Township's activities, events, programs and operations by subscribing to our News and Notices.